???? Kharadi-Keshav Nagar Bridge Update: Another Delay? ????
Many of you requested an update on the Kharadi-Keshav Nagar Bridge, and here we are again! SaudaGhar has covered this topic multiple times, but the never-ending delays force us to revisit it.
???? Bridge Timeline & Delays ????
Work started in April 2022 but was halted due to monsoon.
Restarted in October 2022 but progressing at a snail’s pace.
Tender issued in August 2021 under the PPP model with a ₹23 Cr budget, expected completion in 24 months—yet, 44 months later, it’s still under construction
.Land dispute on the Kharadi side has reportedly slowed down work again.
???? What’s Next? ????
If work doesn’t resume within the next 1-2 months, construction will halt for monsoon, pushing completion to November-December 2024 or beyond. PMC elections are nearing, which might speed up progress.
???? Who is responsible for these delays? Who will compensate daily commuters for their time and fuel wasted? Share your thoughts in the comments!